Date | Progress | |
---|---|---|
Sept 29, 2013 |
Deliverables of Phase 1 (Inception) - Detailed project plan - Project web page |
|
Oct 2013 |
- Mobile app: Customer side - Database setup |
|
Nov 2013 |
- Mobile app: Driver side - Server configuration |
|
Dec 2013 | - Web-based system | |
Jan 13-17, 2014 | First presentation | |
Jan 26, 2014 |
Deliverables of Phase 2 (Elaboration) - Preliminary implementation - Detailed interim report |
|
Feb 2014 |
- Testing and collecting feedback - Refinement |
|
Mar 2014 | - Documentation | |
Apr 20, 2014 |
Deliverables of Phase 3 (Construction) - Finalized tested implementation - Final report |
|
Apr 21 - 25, 2014 | Final presentation | |
May 4, 2014 | Project exhibition | |
June 2, 2014 | Project competition |