Detailed Schedule

Scheduled Completion Milestone Description
2016
October 2
  • Completed

Phase 1 Deliverables

  • Detailed project plan
  • Project website
by October
  • In Progress

Milestone 1

Project study

by November

Milestone 2

Initial preparation

  • Server and database setup
  • User interface
  • 3D body model in Unity
  • Sample data set for development
by December

Milestone 3

Preliminary app

  • Browse and lookup functionality
  • Practices and lessons
  • Tester comments and feedback collection
2017
January 22

Phase 2 Deliverables

  • Preliminary implementation
  • Detailed interim report
by February

Milestone 4

Finalised app

  • 3D body model mapped in Swift
  • Algorithms implementation
by March

Milestone 5

System-wide features

  • System-wide lookup API
  • 3D Touch, dashboard support
  • data loading
by April

Milestone 6

Project wrap-up

  • Optimisation
  • Testing
  • Documentation
April 16

Phase 3 Deliverables

  • Finalised tested implementation
  • Final report