Proposed Timeline

The tentative project schedule is as follows.
Date | Task |
---|---|
1 Sep 2019 – 20 Oct 2019 | Complete Hand Pose Estimation models. |
21 Oct 2019 – 01 Dec 2019 | Working on first prototype for the Hand gesture recognition system. Also work on input stream and output stream implementations. |
24 Dec 2019 – 15 Jan 2020 | Work on the second prototype of the Hand gesture recognition system. |
16 Jan 2020 – 14 Feb 2020 | Work on the final implementation of the Hand gesture recognition system. |
15 Feb 2020 – 31 Mar 2020 | Testing and Debugging |
1 Apr 2020 – 18 Apr 2020 | Real world testing and debugging |
Other than the tentative project schedule, I have also established a number of milestones to be achieved. The details are summarised below:
Date | Milestone | Status |
---|---|---|
29 Sep 2019 | Submission of Inception Deliverables. | Completed |
20 Oct 2019 | Phase 1 complete. A working hand pose estimator ready. | Incomplete |
30 Nov 2019 | First hand gesture recognition prototype ready. | Incomplete |
15 Jan 2020 | Second hand gesture recognition prototype ready. | Incomplete |
2 Feb 2020 | Submission of Elaboration Deliverables. | Incomplete |
14 Feb 2020 | Third hand gesture recognition model read | Incomplete |
19 Apr 2020 | Submission of Final Deliverables. | Incomplete |